Tuesday, October 1, 2013

India in Investment Arbitration LOOP.

A news report in the Indian Express here reports that Khaitan Holdings (Mauritius) Limited (KHML), a Mauritius based investor in Loop Telecom has initiated investment arbitration under the India-Mauritius BIT seeking damages over USD 1 billion for cancellation of its investment in 2G licenses which were cancelled by the Supreme Court of India.  To quote from the report: 

“KHML in the notice said that Supreme Court judgement has held Indian government process to issue licence "seriously flawed and legally untenable, as well as its policy being inherently arbitrary," and neither KHML nor Loop were blamed for this. ‘Despite this, neither adequate or any compensation has been paid to KHML and the spectrum has been subsequently re-bid,’ the notice said.”   

India now features as one of the top nations against which investment treaties claims lie. It all began with the success of White industries’ investment claim against India. Readers who wish to have a detailed analysis of the White Industries’ case may read my article in Kluwer’s Journal of International Arbitration. The abstract along with the citation is: 

“The Indian arbitration landscape is set for a completely new twist in the wake of the first investment arbitration award rendered against India. The decision was rendered in the matter between White Industries Australia Ltd. and the Republic of India in an United Nations Commission on International Trade Law (UNCITRAL) arbitration. This article examines the case, observes the questions which were considered by the tribunal, and discusses the rationale of the tribunal in arriving at its decision. Apart from an analysis of the case, the article also discusses its ripple effect which has already set in.
Ashutosh Ray, 'White Industries Australia Ltd. v. Republic of India: A New Lesson for India' (2012) 29 Journal of International Arbitration, Issue 5, pp. 623–635”

Tuesday, July 9, 2013

Chief Justice of India-Designate, P Sathasivam on Arbitration.

In a recent interview that appeared in Economic Times here, Chief Justice of India(CJI)-designate expressed his dissatisfaction in the way arbitration mechanism has evolved  as an alternate to court litigation. He stated that "Unfortunately even after award, the aggrieved person is not accepting it. When it goes to court, we(the courts) treat it on par with other civil matters, so it gets delayed."  He suggested that the High Court or the Supreme Court should segregate the matters coming from arbitration and direct all such cases to a special bench familiar to the subject. He also suggested that, when dealing with arbitration cases coming to the courts, a time frame be drawn. 

He was of the opinion that commercial matters too, like " green benches" and special benches for death sentence should go to specialised benches earmarked for them. In his view "at least four commercial cities Mumbai, Delhi, Kolkata and Chennai, High Courts must create separate benches for corporate matters."

Australia, in particular has separate bench particularly for arbitration matters which is much narrow when compared to specialised commercial benches as suggested by the upcoming CJI. How far his vision meets reality, only time will tell. However, considering the short span of time for which he will serve as the CJI, for around 10 months, it might be difficult for him to bring in a turnaround in this area when there are already many concerns that will need his attention. 

Thursday, July 4, 2013

Future of Indian Arbitration-Cautiously Optimistic: Says the PWC Report.

PricewaterhouseCooper (PWC) recently released its survey report on Corporate Attitudes and Practices towards Arbitration in India.  

70 respondents comprising Legal Counsels, Legal Heads and other legal personnel of various companies in India were asked to give their feedback on various issues.  The report reveals that a staggering 91% companies include arbitration as opposed to litigation to resolve their future disputes. The top three factors that make arbitration most desired Dispute Resolution (DR) mechanism are 1. Speed, 2. Flexibility and 3. Confidentiality  The report recognizes that institutional arbitration is yet to take off in India and most companies (47%) prefer Ad-hoc arbitration over institutional arbitration (40%). Retired judges of the Supreme Court and High Courts are the most sought-after arbitrators. Among them also, there is only a small club of seasoned arbitrators that the companies choose from.

A very important finding of the survey is that the “Companies in Indian are yet to fully appreciate the tactical significance of the seat of arbitration” This, I believe is very correct because parties and to a large extent even the arbitrators do not have a clear idea of the distinction between seat/place and venue of arbitration. With recent case laws, things appear to be improving but the issue is too important to be pleaded ignorance of.

India followed by Singapore and England are the most favoured seats of arbitration and SIAC/IAC followed by ICC and LCIA finish as the top three institutions for institutional arbitrations.  Although, HKIAC currently has a share of only 3%, I anticipate that this may rise substantially after Honk Kong was notified by the Government of India as a reciprocating country under the New York Convention on enforcement of foreign awards.

Most of the arbitrations in India took more than three years for the completion and the most time consuming activity is constitution of the arbitral tribunal.

Unexpectedly, arbitrators’ fee is among the top three factors that companies attribute to cost of proceedings. What is surprising is, internationally, arbitrators fee comprises not more than 10-15 percent of the total cost involved in arbitration proceedings. The major cost ideally should be attributed to the counsels’ fee and associated expenses.  A report in 2009 by the Commission on Arbitration of the ICC (International Chamber of Commerce) had found that such costs amounted to an average of 82 percent of the total arbitration costs.

Although the future of arbitration is optimistic, companies were dissatisfied up to three times more with the arbitrations happening in India as opposed to arbitrations happening in a foreign seat.  The report says that “though India is a preferred choice as a seat of arbitration, however in practice it is not” The report also suggests that use of expert witness is not very common in India and nearly half of the companies have never used them in their arbitrations.

The report recognizes that “Arbitration remains a preferred dispute resolution mechanism, despite certain loopholes and shortcomings in the arbitration environment in India. “

Wednesday, July 3, 2013

Guest Post: The Kishanganga Dispute and the Partial Award rendered by the PCA: What it means for India?

Below is a guest post by Rishav Banerjee. He is a graduate of Gujarat National Law University and did his masters from  University of Cambridge. The post discusses the partial award that was rendered by Permanent Court of Arbitration in India's favour in an arbitration between India and Pakistan. This article written by Shashank Kumar may also be of interest to the readers. 


Factual Background:
The Kishanganga dispute stems from the construction of a dam as planned by India on the Kishangaga River which is a tributary of Jhelum (one of the Western Rivers allocated to Pakistan under the Indus Water Treaty).

Legal Framework:
Article III(2) of the Indus Water Treaty (IWT) is the provision of main concern in the dispute which talks about India’s compliance  with its obligations to “let flow all waters of the Western Rivers” and its limited exceptions. India strongly relies on the IWT provisions that provides for inter-tributary diversions.  
The other aspect of the dispute arises out of the interpretation of Annexure D and its restrictions on the design and operation of Run of River Plants, such as the KHEP, including in particular the restrictions on dead and live storage, set out in paragraphs 2(a), (b) & (g), 8, 14 and 15 of Annexure D of the IWT. Paragraph 2(a) and (b) define the distinction between “Dead Storage” and “Live Storage” respectively, while paragraph 2(g) sets out the criteria for a ‘Run-of-River Plant’. Paragraph 14 makes Paragraph 18 and 19 of the Annexure E applicable to the filling of Dead Storage. Paragraph 8 sets out certain design restrictions, whereas paragraph 15 imposes further operational restrictions. Based on these provisions, Pakistan submitted that India’s proposal of drawdown flushing as part of KHEP’s design and operation is disallowed under the IWT.

Dispute Resolution: Arbitration at the Permanent Court of Arbitration
Pakistan commenced the process for resolution of the dispute under Article IX (2), (3), (4) and (5) of the Treaty. In May 2005, Pakistan raised the following six objections:
1. “Whether India’s proposed diversion of the Kishanganga (Neelum) into another tributary, i.e. the Bonar-Madmati Nullah, being one central element of the Kishanganga Plant, breaches the legal obligations India owes Pakistan under the Treaty, as interpreted and applied in accordance with international law, including India’s obligations under Article III(2) (let flow all the waters of the Western rivers and not permit any interference with those waters”) and Article IV(6) “maintenance of natural channels?”
2. Whether the design of the plant is in conformity with Paragraph 8(a) of Annexure D to the Treaty?
3. Whether the design of the Kishanganga Plant is in conformity with Paragraph 8(c) and Paragraph 8(f) of Annexure D to the Treaty?
4. Whether the design of the plant is in conformity with Paragraph 8(d) of Annexure D to the Treaty?
5. Whether the design of the plant is in conformity with Paragraph 8(e) of Annexure D to the Treaty?
6. Whether under the Treaty, India may deplete or bring the reservoir level of a run-of-the-river plant below dead storage level in any circumstances except in the case of an unforeseen emergency?[1]
It is the second time Pakistan sought resolution of a dispute through the dispute settlement mechanism contained in the IWT and the first time through the International Court of Arbitration. In the Kishanganga case, both "difference" and "dispute" has come into play.[2] Pakistan had proposed the reference of certain technical issues to the Neutral Expert and had sought legal interpretation on two major parameters concerning the diversion of Kishanganga water for a power project from the Court of Arbitration. Although the two countries have rejected each other’s nominees for the Court of Arbitration, they have decided to set up a panel comprising a chairman, a legal member and an engineer to select the umpires, by drawing lots.[3] The court comprised of six members and was presided over by a chairman which was Judge Stephen Schwebel in this case. It is important to reiterate that the Court of Arbitration route is taken only when the issue does not pertain to technicalities and concerns a legal dispute over the interpretation of the IWT.
In its Request for Arbitration, Pakistan stated that the Parties had failed to resolve the “Difference” concerning KHEP by agreement pursuant to Article IX(4) of the Treaty. Pakistan identified “two questions that are at the centre” of the dispute in the following manner:
1) Whether India’s proposed diversion of the river Kishenganga (Neelum) into another Tributary, i.e. the Bonar-Madmati Nallah, being one central element of the Kishenganga Project, breaches India’s legal obligations owed to Pakistan under the Treaty, as interpreted and applied in accordance with international law, including India’s obligations under Article III(2) (let flow all the waters of the Western rivers and not permit any interference with those waters) and Article IV(6) (maintenance of natural channels)? (First dispute)
2) Whether under the Treaty, India may deplete or bring the reservoir level of a run-of river Plant below Dead Storage Level (DSL) in any circumstances except in the case of an unforeseen emergency?[4] (Second Dispute)
With regards to the first dispute Pakistan submitted before the court that by making the proposed diversion at KHEP India has breached its obligation under the IWT in four manners:
1)      India has violated its obligations under Articles III (1) and (2) to let flow all the waters and not to permit any interference with these waters, as the tightly constrained exceptions to these obligations, including the right to use the waters of the Jhelum to generate hydroelectric power in accordance with Annexure D, does not establish a right to operate a project that permanently diverts the entirety of the waters of the Kishenganga to another Tributary of the Jhelum.[5]
2)      Even if Paragraph 15(iii) of Annexure D did establish some right to divert, such right is limited by the express wording of Article III(2) of the IWT, restricted in the case of the Jhelum ‘to the drainage basin thereof’.
3)      The planned diversion is not in compliance with the strict criteria set out in Paragraph 15(iii) of Annexure D, as it is not necessary and as it causes adverse impact to ‘the then existing Agricultural Use or hydro-electric use’.
4)      By the planned diversion India would also breach its obligation under Article IV (6) of the IWT to ‘use its best endeavours to maintain the natural channels of the Rivers’.[6]
With respect to the second dispute, Pakistan submitted that India’s proposed design of the KHEP, including its ability to drain the reservoir behind the Plant and then halt the flow of water for as long as it takes to refill the reservoir is prohibited under Annexure D, which sets out a series of restrictions on the design and operation of Run-of-River Plants, including in particular with respect to the height and size of the outlets, gates and water intakes, as well as with respect to the water impounded behind the Plant.[7]
India in response to Pakistan’s arguments submitted that KHEP fully complies with its rights and obligations under the IWT and that the second dispute is inadmissible as it constitutes a ‘difference’ which is subject to referral to a Neutral Expert in accordance with Article IX(2) of the IWT before it can be submitted to arbitration.[8] With regards to the first dispute, India argued that it is expressly permitted by Article III(2) and Annexure G to generate hydroelectric power and that this right is limited only with respect  to the manner in which it can be exercised by Annexure D.[9] India further submitted that that Annexure D contained enabling provisions granting the right to construct Run-of-River Plants involving inter-tributary transfers subject to the then existing agricultural or hydroelectric uses by Pakistan not being adversely affected.[10] According to India, these uses are to be assessed by reference to KHEP’s purported conception in the 1950’s.[11] India also argued that in any event, the areas that Pakistan claims would be adversely affected by the operation of the KHEP are a part of Kashmir which forms an integral part of India in accordance with its constitution.[12]

Order on Interim Measures:
Pakistan submitted an application for the indication of provisional measures. It prayed before the Court to pass an interim order restraining India from proceeding further with the planned diversion of the river Kishenganga/Neelum until such time as the legality of the diversion is finally determined by a Court of Arbitration.[13] The Court of Arbitration after a site visit in June 2011 issued its Order on the Interim Measures Application on September 23, 2011. In paragraph 152, which is the operative provisions of the order, the Court ordered that “It is open to India to continue with all works relating to the Kishenganga Hydro-Electric Project, except India shall not proceed with the construction of any permanent works on or above Kishenganga/Neelum riverbed at the Guez site that may inhibit the restoration of the full flow of that river to its natural channel”[14] and that both the Parties “shall arrange for periodic joint inspections of the dam site at Guez in order to monitor the implementation” of that order[15].

Partial Award:
On February 18, 2013 the Court of Arbitration rendered the Partial Award in respect of the dispute between India and Pakistan under the IWT concerning the two disputes as stated above.
In its Partial Award, which is final with respect to the matters decided therein, without appeal and binding on the Parties, the Court of Arbitration unanimously decided:
1. The Kishenganga Hydro-Electric Project (KHEP) constitutes a Run-of-River Plant under the Treaty, and India may accordingly divert water from the Kishenganga/Neelum River for power generation by the KHEP in the manner envisaged. However, when operating the KHEP, India is under an obligation to maintain a minimum flow of water in the Kishenganga/Neelum River, at a rate to be determined by the Court in a Final Award.
2. Except in the case of an unforeseen emergency, the Treaty does not permit India’s reduction below “Dead Storage Level” of the water level in the reservoirs of Run-of-River Plants located on the rivers allocated to Pakistan under the Treaty. This ruling does not apply to Plants already in operation or under construction (whose designs have been communicated by India and not objected to by Pakistan).[16]
While adjudicating the first dispute and coming to the conclusion that the IWT expressly permits the transfer of water by India from one tributary of the Jhelum to another for the purpose of generating hydro-electric power, subject to certain conditions, the Court of Arbitration found that this right is not circumscribed by the Treaty’s restriction of Indian uses on the Western Rivers to the drainage basin of those rivers but the restriction relates to where water may be used, and is not violated by the use outside of the drainage basin of electricity generated from the water.[17] Thereafter the Court scrutinized the provisions under the IWT which requires the Parties to maintain the natural channels of the rivers and its effect on inter-tributary transfers wherefore the Court observed that this obligation involves maintaining the river channels’ physical capacity to carry water, and does not require maintaining the timing or volume of the flow in the river and thus accordingly, this obligation does not limit India’s right to transfer water for the purpose of generating hydro-electricity.[18] On deciding whether the KHEP meets the express condition of such transfers as mentioned in the IWT, the Court observed that the KHEP is a Run-of-River Plant within the definition of “Run-of-River Plant” under the IWT and which is also a requirement under Annexure D.[19] Finally, the Court found that the KHEP’s inter-tributary transfer is “necessary,”[20] as required by the Treaty, for the generation of hydroelectric power, as power can be generated on the scale contemplated by India in this location only by using the 665 metre difference in elevation between the dam site on the Kishanganga/Neelum and the place where the water is released into the Bonar Nallah.[21]

The Court thereafter went to discuss another requirement of Paragraph 15(iii) which is “then existing Agricultural Use or hydroelectric use by Pakistan” on the downstream reaches of the Kishanganga/Neelum should not be affected by the inter-tributary transfer required for KHEP. The Court while determining the fact referred to Article 31(1) of the Vienna Convention on the Law of Treaties and observed that the provisions focus on the operation of hydro-electric plants and the implication that the determination of “then existing” uses should take place on an ongoing basis throughout the operational life of the plant.[22] After examining the object and purpose of the IWT, the court observed that the IWT gives Pakistan a priority to use the waters of the Western Rivers as well gives India the right to generate hydro-electric power on the Western Rivers.[23]
Coming to the question of application of the IWT to KHEP, the Court rejected both the “ambulatory approach” as suggested by Pakistan and the “critical period” approach as suggested by India and noted that the proper interpretation of the treaty combines elements of both the approaches.[24] The Court considered the critical period of the KHEP and the NJHEP i.e. the period in which the parties not only planned the projects but also took major steps to realize the projects. After reviewing the evidence provided by the Parties, the Court found that the critical period of KHEP was in 2004-2006 in comparison to NJHEP which was in 2007-2008 and thus the Court decided that India’s right to divert waters of the Kishenganga by KHEP is protected by the Treaty.[25] However according to the Court India’s right to divert the Kishenganga/Neelum is not absolute as it is subject to the restrictions specified in the IWT and by the relevant principles of customary international law.[26] Paragraph 15(iii) obliges India to operate its projects in such a way as to avoid adversely affecting Pakistan’s then existing agricultural and hydro-electric uses. The Court thus observed that Pakistan retains the right to receive a minimum flow of water from India in the Kishenganga/Neelum riverbed at all times.[27] The Court found that this right also stems from customary international environmental law, and that it considered that the IWT must be applied in light of contemporary international environmental law principles.[28]
With regards to the determination of the minimum flow of water downstream, the Court deferred it till the Final Award as the data provided by the Parties were insufficient. Thus the Court also ordered the Parties to provide additional data concerning the impacts of a range of minimum flows at the KHEP dam on, (for India), (a) power generation at the KHEP; and (b) environmental concerns from the dam site at Gurez to the Line of Control; and, (for Pakistan), (a) power generation at the NJHEP; (b) agricultural uses of water downstream of the Line of Control to Nauseri; and (c) environmental concerns at and downstream of the Line of Control to Nauseri.[29]

While adjudicating the second dispute, where India raised two objections to the admissibility of the Second Dispute, the Court while dismissing India’s objections ruled that the Second Dispute is admissible as according to the Court, the IWT provides for disagreements between the Parties to be resolved either by a seven-member court of arbitration[30] or by a neutral expert and once constituted, a court of arbitration has power to consider any question arising out of the IWT which also includes technical questions.[31]

On the issue of the permissibility of the Depletion of Reservoirs for Drawdown Flushing, the Court after examining three aspects of the context of the IWT with respect to drawdown flushing, concluded that the IWT prohibits depletion below Dead Storage Level of the reservoirs of Run-of-River Plant (and, correspondingly, drawdown flushing)[32] by referring to a provision of the Treaty Annexure dealing with storage works, which states that “the Dead Storage shall not be depleted except in an unforeseen emergency”.[33] After critically reviewing the technical documents submitted by the Parties and the testimony of the experts presented during the arbitration, the Court observed that drawdown flushing is only one means of sediment control and that hydroelectricity may be generated without flushing.[34]

Concluding Remarks:
The need for high level and sustained political leadership is required for joint benefits of both countries. In the author’s opinion, it will be desirable to think ahead and conceptualize building on the IWT, 1960. The use of reset terms by PCA for both India and Pakistan and the use of enhanced diplomatic methodology for mutual sustenance would be a good approach in troubled times to settle the disputes peacefully.





[1] Dr. Shaheen Akhtar, “Emerging Challenges to IWT: Issues of compliance & transboundary impacts of Indian hydroprojects on the Western Rivers”, p. 45, available at <http://www.irs.org.pk/f310.pdf> accessed on January 5, 2013 at 4 p.m.  p.46-47.
[2] Supra 1, p. 50.
[3] Ibid.
[4] Pakistan’s Request for Arbitration, para. 4.
[5] Pakistan’s Request for Arbitration, para. 4(a) ; Pakistan’s Memorial, para. 1.12.
[6] Ibid.
[7] Hearing Tr., (Day 4), 23 August 2012, at 190:18-20.
[8] India’s Counter-Memorial, para. 7.2; India’s Rejoinder, paras. 4.2, 4.4.
[9] India’s Counter-Memorial, para. 4.39.
[10] India’s Counter-Memorial, para. 4.78, referring to Record of the 93rd Meeting of the Commission, New Delhi, 9-13 February 2005, (Annex PK-29), para. 38.
[11] India’s Counter-Memorial, para. 4.23. According to India, Paragraph 15(iii) was intentionally inserted in the Treaty on the basis of a 1954 hydro-electric survey of the Indus basin carried out by India’s CWPC, which identified the possibility of building a hydro-electric scheme on the Kishenganga. See India’s Counter- Memorial, para. 4.70.
[12] India’s Counter-Memorial, para. 6.49.
[13] Pakistan’s Request for Arbitration, para. 54(a).
[14] Paragraph 152(1) of the Order on Interim Measures.
[15] Paragraph 151(2) of the Order on Interim Measures.
[16] PCA Press Release Indus Waters Kishenganga Arbitration (Pakistan v. India), Court of Arbitration issues Partial Award (“Partial Award”) available at <http://www.pca-cpa.org/shownews.asp?nws_id=351&pag_id=1261&ac=view>.
[17] Ibid., para.369.
[18] Ibid., para.373.
[19] Ibid., para.383.
[20] Ibid, paragraph 396 and 398.
[21] Ibid p. 369.
[22] Partial Award, supra 16, para 404.
[23] Ibid, para 410 and 411.
[24] Ibid, para 433.
[25] Ibid, para 442.
[26] Ibid, para 445.
[27] Ibid.
[28] Partial Award, supra 16, para 447- 453.
[29] Supra 16.
[30] IWT, Art. IX(1).
[31] Partial Award, supra 16, para 487.
[32] Partial Award, supra 16, para 514-515.
[33] IWT, paragraphs 18 and 19 of Annexure E.
[34] Partial Award, Supra 16, para 520. 

Friday, May 31, 2013

Recent Trends in Investment-State Dispute Settlement (ISDS): Why India Should be Worried

The latest UNCTAD report on trends in investment disputes says that last year saw a record 95 claims filed against States. This brings the total number of known treaty based cases to 518. Unsurprisingly, claimants from the United States account for 123 (or 24%) of all such cases. 42 decisions were given in 2013 of which 9 resulted in the award of $ 1.77 billion dollars.

The more worrying trend, which lends credence to the calls for reform is that 61 claims last year were against developing countries. Countries in financial crisis were also a target for investment claims with two Chinese investors bringing a claim against the Belgian government for its treatment of Fortis. A Cypriot bank brought claims against the Greek government arguing the bailing out Greek banks discriminated against its Greek subsidiary. Investors also challenged environmental measures taken by governments over the last year. Such claims should force us to revisit the question of the balance of power between Investors and States in BITs. This problem is magnified in case of practices like third party funding, where specialized firms finance Investor Claims in return for a share in future damages. The discontent with existing ISDS mechanisms is widespread and calls for reform are getting louder. It has been reported that mediation is proving to be an attractive option for resolution of such disputes (for a detailed analysis see the Kluwer blog article here).

It is in this context, that we look at what the UNCTAD report says about India. In January, it was reported that India was putting on hold all existing BIT negotiations in light of a spate of claims following the White Industries judgment. As many as 7 investors had filed investment claims against India in 2012, and India ranks as the country with the second highest claims after Venezuela (9). Despite this it seems that India is in negotiations to sign a BIT with the United States.

I had previously argued that investor claims notwithstanding India should in fact join the ICSID. I still stand by that position, because ICSID offers a way of resolving India's investment disputes as well as allowing Indian investors abroad to file claims against other States. But the problem with the current Indian position is that it is unclear if Investment awards can be enforced under the Arbitration and Conciliation Act, 1996. While the government has announced a rethink on BITs as far back April 2012, the process has been far from transparent, and little is known about what policy/legislation if any is being formulated to address this reconfigure India's BITs.

With India negotiating a BIT with the US- a country who's investors are responsible for a fourth of all investment claims- India should not only has the opportunity to reform its own BIT policy but also play a leadership role in evolving new mechanisms for developing countries in balancing the power between Investors and States.

Monday, May 27, 2013

Off-topic - TN's renewed claims over Katchatheevu

The Hindu (May 27) has published an op-Ed by me titled 'Chasing a boat we missed long ago'. This piece discusses the legal aspects of Tamil Nadu's renewed claims over Katchatheevu Island, which is currently in Sri Lankan possession. In this piece, I raise two key points: first, litigation before the Supreme Court on this matter is futile since any order issued by Supreme Court will not be binding on Sri Lanka; second, under international law (which governs territorial disputes between states), any claim that Tamil Nadu may persuade the Centre to make is likely to be a weak one.

The full text of the article may be accessed here.

Tuesday, May 21, 2013

Sahara Withdraws From IPL Over Arbitration Issue

Sahara, BCCI: No more getting back?

As per the latest reports here and here, Sahara has withdrawn from the Indian Premier League (IPL) which has already been in much controversy for sometime now. If that was not enough, Sahara even plans pull out of the sponsorship of the Indian cricket team from the next year. The reason for the withdrawal is supposedly Board of Control for Cricket in India (BCCI) not keeping its promise to arbitrate the disputes. 

The matter of the dispute goes something like this: Sahara had bought "Pune Warriors" franchise for an amount of rupees 1702 crore for 10 years. However, dispute arose regarding the reduction of the franchise fee as initially there were 94 matches which was later reduced to 64 matches. According to the report, Sahara paid around 20 percent of the year franchisee fee, an amount of Rs 170 crore in January and was about to pay the remaining amount by May 19 but failed. The IPL governing council then decided to encash the bank guarantee.

Sahara claims that the BCCI not only turn a deaf ear to its pleadings for arbitration and reducing the franchise fee but also rejected appointment of several arbitrators . It did not recommend any instead. Allegedly, the appointment of a former Chief Justice of India was also rejected by BCCI after sitting over the request for several months. 

The IPL has been hitting new lows with every passing day.

Sunday, May 19, 2013

FIAA / SIAC Advocacy Workshop on Questioning of Expert Witnesses in International Arbitration

Below is the announcement by FIAA - Foundation for International Arbitration Advocacy for its next Advocacy Workshop on "Questioning of Expert Witnesses in International Arbitration". The program is being conducted in collaboration with SIAC. 
On a personal note, it is one of the most relevant and effective programs as it equips the participants to argue on advanced and complex arbitration matters. The program would be big advantage for the people residing in Singapore and neighbouring Asian cities. The program has a limited intake so as to make it very productive. 

FIAA - Foundation for International Arbitration Advocacy has opened registration for its next Advocacy Workshop on "Questioning of Expert Witnesses in International Arbitration", which will be held 20 – 22 June 2013 at the Hilton Hotel in Singapore.  FIAA is pleased to be running this workshop in conjunction with SIAC – Singapore International Arbitration Centre and with the support several sponsors.

This learning-by-doing workshop will provide international arbitration practitioners with skills and techniques for examination, cross-examination and witness conferencing involving expert witnesses. Participants will have a unique opportunity to improve their advocacy skills by:
  • working with accounting experts from leading firms;
  • engaging in exercises and simulations based on a mock arbitration case, including a full day witness hearing; and
  • obtaining direct feedback and practical advice from leading international arbitration practitioners and advocacy instructors. 

Early registration is recommended as this workshop is limited to 24 participants. For full workshop and registration details, please see the attached Program or visit www.fiaa.com.

Saturday, May 18, 2013

SIAC Opens up in India. It's First Outside Singapore.

The Singapore International Arbitration Centre (SIAC), for the first time stepping outside the island nation, has opened up its new office in the financial capital of India, Mumbai. India’s image as a country significantly contributing to international arbitration case load is being increasingly recognized. World’s major arbitration institutes want their share of this big pie. Few years back LCIA too had chosen India to open its first off shore office: LCIA India. However, unlike LCIA India, SIAC shall not be having separate arbitration Rules for India. India, as a seat for international arbitration does not seem to be a preferred choice among the international corporations.

Mr. Vivekananda N., Head (South Asia) of SIAC would be heading this office. Here are his answers to few questions with regard to SIAC India.

This is SIAC's first offshore office, why was India chosen?

SIAC has continued to focus on engaging with the Indian market since 2005.

The years 2009 and 2010 saw the number of India-related cases at the SIAC grow by about 100% in 2009 (24 cases in 2009 as compared to 11 in 2008) and another 50% in 2010 (36 cases in 2010). The number of cases involving Indian parties was the single largest contingent of cases from a single non-Singaporean nationality at the SIAC for these years.

As a consequence of these developments and the positive response we received from the community in India, it was felt that it would be useful to maintain a presence in India through an office to reach out to lawyers and users in India. With this in mind, in mid-2011, the SIAC Board of Directors headed by Dr Michael Pryles decided to commence efforts to explore the opening of an office in India.

Would SIAC have separate rules to govern arbitrations in India?

The India office of the SIAC is not involved in the administration of cases in India. The office is a subsidiary of the SIAC. It is charged with functions of interacting with our current and potential users and sharing information on international arbitration jurisprudence and practice with a view to marketing SIAC’s and Singapore’s capabilities in this regard.

What would be the role of SIAC India office?

Our primary focus will remain the provision of practical information necessary to lawyers and corporate users for the effective use of international arbitration as a dispute resolution mechanism. Making arbitration cost-effective, timely and efficient for Indian and other parties and letting them know that this is imminently possible outside of courts is of paramount importance for the SIAC.

What are your plans for the coming 3 years?

The Indian market is fairly widespread across industry sectors and cities. The office provides us with the perfect opportunity to reach out to lesser known sectors and the smaller cities in India though Mumbai, Delhi and Bangalore will continue to remain primary areas of focus.

The office will continue our efforts to obtain continuous feedback on our services as an arbitral institution, such feedback being crucial to maintaining and constantly improving the quality of our case management and administration capabilities.

The office will also provide us with the opportunity to work more closely with the judiciary and the government in India on policy initiatives, regular exchange of ideas on live issues, legislative change, amongst others.

Last but not the least, we also look forward to working with the Indian lawyers of tomorrow at universities to train them in international arbitration practice and actively work towards developing a dynamic arbitration bar in India.

Better awareness, understanding and practice of international arbitration in India is in the best interest of everyone involved, the users, lawyers, the judiciary and arbitral institutions.

How many cases at SIAC involved Indian parties in recent past?

In 2012, about 21% of cases at SIAC involved at least one Indian party. I attach a Statistical Report on our India-related cases. Some interesting facts:
(i) The number of new cases at SIAC has gone up by 25% from 2011 to 2012
(ii) The number of new cases involving at least one Indian party has grown tenfold in the period from 2001 to 2012 and by almost 50% from 2011 to 2012
(iii) The monetary quantum of disputes involving at least one Indian party has similarly gone up by 200% from 2011 to 2012
(iv) The largest case for 2012 was a case involving an Indian party and involved a sum in dispute of SGD 1.5 billion
(v) The average dispute amount at the SIAC for 2012 in cases involving Indian parties was SGD 41.88 million. Even without the largest case being accounted for, the average sum in dispute for cases involving Indian parties went up by 66% from 2011 to 2012. This implies that not only are more Indian parties opting to arbitrate at the SIAC but that higher value contracts involving Indian parties increasingly provide for arbitration at the SIAC.
The link to the full report is below: 

Statistical Report of Singapore International Arbitration Centre (SIAC) on India 2012

Call for Papers: Indian Journal of Arbitration Law

Below is the call for papers for the Indian Journal of Arbitration Law. 

The Indian Journal of Arbitration Law is pleased to announce its upcoming issue (Volume 2: Issue 2), which is to be published in September this year. The Board of Editors cordially invites original, unpublished submissions for publication in the following categories:
- Articles
- Notes
- Comments
- Book Reviews
Manuscripts may be submitted via email to editor.cartal@gmail.com latest by 31st July 2013.

Editorial policy and submission guidelines are available here.



counter on blogger